INS Vikrant model at DefExp 2014 |
The Navy, however, wants its next home built carrier to be much larger than INS Vikrant; it wants a 65,000 ton, possibly nuclear powered, super-carrier that can operate heavy aircraft, such as AEW&CS platforms for more effectively protecting the carrier battle from enemy fighters and cruise missiles.
The Indian Navy (IN) currently operates two aircraft carriers - INS Virat and INS Vikramaditya. INS Virat's retirement in 2016 would reduce INs carrier strength to one. The Navy would then operate with a single carrier for at least the next 2 years, till INS Vikrant is commissioned in end 2018.
From 2019 onwards, for the next 10-15 years till the super-carrier is delivered, IN will operate two aircraft carriers. Factoring in the requirements for maintenance and refits, assured availability would be limited to just one.
The navy would need a third (reserve) aircraft carrier in order to operate two carrier battle groups, required to secure both the western and the eastern coasts. Reputed analysts like Ashley Tellis believe that India needs to monitor growing PLAN activity in the Indian ocean, which would be best done using a carrier battle group, not shore based aircraft.
A CSL official told The Hindu, "A follow-on carrier would be advantageous for the Navy, as there would be no time lost on detailed design, development of specialist material, technology, honing of skills of the workforce and so on. Since the Navy desires to operate two carrier task forces at any given time, it would be a good option to exercise."
Budgetary Constraints
There must be a good reason why the Navy has not shown interest in a follow-up Vikrant class carrier, and that reason could only be a tight budget! However, a solution to budgetary constraints may well lie in the inevitable project execution delays associated with new class ships in general and an ambitious super carrier in particular.
The super-carrier, which received its first budgetary sanction for design work during the May 13, 2015 DAC meeting, may not materialize for at least 20 years (2035) assuming it's nuclear powered, by which time the refurbished INS Vikramaditya would be heading towards the scrapyard. (Its 30-year designed life would end in 2041)
The following are three good reasons why the Navy's coveted super carrier could take a long time to join the fleet.
Extended Construction Period
INS Vikrant is expected to be delivered to the Indian Navy by end 2018, over 9 years after its keel was officially laid in February 2009. (Order for the ship was placed in 2002-03. Construction started in 2006, but stalled due to paucity of steel. It picked up pace after Defense Metallurgical Research Laboratory (DMRL) and the Steel Authority of India (SAIL) developed carrier-grade steel indigenously.)
Clearly, a first of its class 65,000 tonnes nuclear powered, super carrier capable of launching heavy aircraft using EMALS would likely take 10-12 years to build.
Extended Harbor and Sea Trial Phase
The Navy wants the new super carrier to be nuclear powered. That would require development of new nuclear reactors and propulsion system. Harbor and sea trials of such a nuclear powered carrier would take a long time. Longer perhaps than for INS Arihant, which was launched in 2009, and is still undergoing sea trials 6 years later.
Mastering CATOBAR air operations
Air operations on the new carrier which will feature catapult assisted T/O will differ substantially from air operations on INS Vikramaditya and INS Vikrant which feature ski-jump short take-off. IN has no experience in designing a CATOBAR carrier. The last CATOBAR carrier that it operated, INS Vikrant, belonged to the Jurassic era of naval aviation. A new shore based training facility (SBTF) would be required.
For those who still think my construction period estimate of 20 years is an exaggeration, here is the clincher - What if Saint Anthony returns as the RM!!! Haaaah!
Conclusion
Make in India is fine, but how much sense does making a single ship of a class make? The IAF gets lambasted in the media for ordering just 40 Tejas LCAs, when it actually doesn't want any. Here we have the Navy ordering just one ship of a class that it designed for itself! And every one thinks the Navy is the smarter of the two services!
No comments:
Post a Comment