FIGHTER AIRCRAFT 
 | 
      
       
STATUS 
 | 
      
       
INDUCTION INTO SERVICE 
 | 
     
      | 
       
MMRCA 
 | 
      
       
Specifications, contractual setup and workshare has
      been finalised with HAL by Dassault Aviation. Initial 18 to be procured
      as fly-away and remaining 108 to be licensed-produced by HAL in Bengaluru 
 | 
      
       
If a contract is signed this year,  
      then the first batch of aircraft  
      would be delivered by 2017. 
 | 
     
      | 
       
PMF (FGFA) 5th Generation Fighter 
 | 
      
       
PMF preliminary design phase (PDP) completed in June
      2013. Series production expected to commence in 2022. Su-30 MKI would
      have ended by then. 
 | 
      
       
To take place in 2022-2025  
      time frame. HAL to commence  
      flight testing of IAF variant in  
      2018 
 | 
     
      | 
       
Sukhoi Su-30 MKI 
 | 
      
       
Total of 272 ordered till date. HAL will complete
      delivery of 222 aircraft it has on order by 2019-2020 
 | 
      
       
More than 150 Su-30 MKI  
      are in IAF service 
 | 
     
      | 
       
Mirage 2000 Upgrade 
 | 
      
       
Two aircraft being upgraded at present in France.
      Remaining 47 aircraft to be upgraded by HAL in Bengaluru 
 | 
      
       
Upgrade of all aircraft scheduled  
      to be completed by 2021. 
 | 
     
      | 
       
MiG 29 Upgrade 
 | 
      
       
First of upgraded aircraft to enter service this year 
 | 
      
       
Upgrade of 60 plus aircraft  
      will be completed by middle  
      of 13th plan 
 | 
     
      | 
       
Jaguar Upgrade 
 | 
      
       
Contract signed with HAL 
 | 
      
       
Upgrade of all aircraft will  
      be completed by end of  
      13th plan 
 | 
     
      | 
       
LCA ‘Tejas’ Mk1 
 | 
      
       
FOC to be obtained by end of 2014 
 | 
      
       
Two squadrons to be inducted  
      by end of 12th plan 
 | 
     
      | 
       
TRAINERS 
 | 
      
       
STATUS 
 | 
      
       
ENTRY INTO SERVICE 
 | 
     
      | 
       
Pilatus PC-7 Mk II 
      Basic Trainer 
 | 
      
       
RFI for additional 106 trainers to be acquired through
      ‘buy & make (Indian)’ has been released 
 | 
      
       
Already in service with  
      37 trainers delivered as  
      of May this year 
 | 
     
      | 
       
HJT 36 Sitara Intermediate Jet Trainer (IJT) 
 | 
      
       
IOC yet to be obtained 
 | 
      
       
Entry into service likely to be  
      delayed by a few years 
 | 
     
      | 
       
Hawk Mk-132 Advanced Jet Trainer (AJT) 
 | 
      
       
Orders for 20 more Hawks for Surya Kiran display
      likely to be placed by next year 
 | 
      
       
All 66 from first order have  
      been delivered. Deliveries  
      underway as part of additional  
      contract for 40 
 | 
     
      | 
       
HELICOPTERS 
 | 
      
       
STATUS 
 | 
      
       
ENTRY INTO SERVICE 
 | 
     
      | 
       
Light Utility Helicopter (LUH) 
 | 
      
       
First prototype likely to be ready this year 
 | 
      
       
Induction into service likely to  
      take place by end of 12th plan 
 | 
     
      | 
       
Reconnaissance & Surveillance Helicopter 
 | 
      
       
Winner yet to be declared 
 | 
      
       
NA 
 | 
     
      | 
       
Advanced Light Helicopter 
 | 
      
       
Dhruv Mk4 deliveries currently underway 
 | 
      
       
All Dhruv helicopter deliveries to completed  
by end of 12th plan 
 | 
     
      | 
       
Light Combat Helicopter (LCH) 
 | 
      
       
65 on order for IAF 
 | 
      
       
IOC likely to be obtained by 2015 
 | 
     
      | 
       
Medium Lift Helicopter 
 | 
      
       
All 71 Mi-17V-5 helicopters to be delivered by next
      year 
 | 
      
       
80 helicopters from previous  
      order are already in service 
 | 
     
      | 
       
Heavy Lift Helicopter 
 | 
      
       
Boeing Ch-47 D Chinook declared winner 
 | 
      
       
Order for 15 helicopters has  
      been delayed 
 | 
     
      | 
       
Attack Helicopter 
 | 
      
       
Boeing AH-64 D Apache block 3 selected 
 | 
      
       
Order for 22 helicopters has  
      been delayed 
 | 
     
      | 
       
VVIP Helicopters 
 | 
      
       
Order for 12 VVIP AW 101 helicopters terminated in
      January this year 
 | 
      
       
Three helicopters delivered  
      to the IAF before the order was terminated 
 | 
     
       | 
       | 
       | 
       | 
       | 
     
     